PLEASE PLACE THE FOLLOWING DESCRIBED ITEM ON THE AGENDA FOR THE 11/7/2023 MEETING OF THE MAYOR AND BOARD OF ALDERMAN.
Item for Approval:
title
Order to authorize and approve Contractor’s Estimate Package #15 from T. L. Wallace Construction Company for $88,557.61 on the Pearl-Richland Intermodal Connector Bridge Project.
end
Department Represented: Mayor’s Office
Back Up Data: Estimate Package Attached
Purchasing Approval: Budget Acct#: 018-602-714
(MUST be initialed by Leia Cooper for purchases over $5,000, which require Board approval, prior to submission to the Mayor.)
SUBMITTED BY: Kathy Bourgeois 10/31/2023
MAYOR’S APPROVAL:
NOTE: SAVE COPY OF REQUEST AND BACK-UP FOR YOUR RECORDS