Title: Order to authorize and approve Contractor's Estimate Package #15 from T. L. Wallace Construction Company for $88,557.61 on the Pearl-Richland Intermodal Connector Bridge Project.
Sponsors: Kathy Bourgeois

PLEASE PLACE THE FOLLOWING DESCRIBED ITEM ON THE AGENDA FOR THE 11/7/2023 MEETING OF THE MAYOR AND BOARD OF ALDERMAN.

 

Item for Approval:

title

Order to authorize and approve Contractor’s Estimate Package #15 from T. L. Wallace Construction Company for $88,557.61 on the Pearl-Richland Intermodal Connector Bridge Project.

end

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Department Represented:  Mayor’s Office

Back Up Data:  Estimate Package Attached

Purchasing Approval:                     Budget Acct#:  018-602-714                     

(MUST be initialed by Leia Cooper for purchases over $5,000, which require Board approval, prior to submission to the Mayor.)

 

SUBMITTED BY:   Kathy Bourgeois                       10/31/2023

 

MAYOR’S APPROVAL:                        