PLEASE PLACE THE FOLLOWING DESCRIBED ITEM ON THE AGENDA FOR THE 9/5/2023 MEETING OF THE MAYOR AND BOARD OF ALDERMAN.
Item for Approval:
title
Order to approve July Contractor’s Estimate #13 from T. L. Wallace Construction for $672,012.13 on the Pearl-Richland Intermodal Connector project.
end
Department Represented: Mayor’s Office
Back Up Data: Contractor’s Estimate #13
Purchasing Approval: Budget Acct#: 018-602-714
(MUST be initialed by Leia Cooper for purchases over $5,000, which require Board approval, prior to submission to the Mayor.)
SUBMITTED BY: Kathy Bourgeois 8/30/2023
MAYOR’S APPROVAL: